Renovating a bathroom in Sweden: rules, cost and a realistic timeline

What do the Swedish industry rules require, what does a bathroom cost in the Gothenburg area and why does it take six weeks, not two? A walkthrough without flattering numbers.

Newly renovated bathroom with tiled walls and a floor drain

The bathroom is the most expensive room per square metre in a home, and the only one where a sloppy job can cost hundreds of thousands of kronor in consequential damage. Here is what actually drives time, price and quality.

The rules you cannot negotiate

A bathroom is a wet room, and in Sweden wet rooms are covered by binding industry rules:

  • BBV (the Swedish Ceramic Council's industry rules for wet rooms) covers ceramic wall and floor tiles
  • GVK covers wet rooms with vinyl flooring
  • Säker Vatten (Safe Water) covers the plumbing installations
  • The regulations of the Swedish National Electrical Safety Board (Elsäkerhetsverket) govern electrical work in wet areas

In practice: the waterproofing layer must be installed by a certified wet-room contractor, and the work must be recorded in a quality document that you receive at handover. Without that document, the insurance company can sharply reduce its payout after a future water leak – and a buyer will ask for it when you sell.

Keep the quality document, the self-inspection record and the invoices together. They are worth money the day you sell.

Is a building permit or notification required?

If you only replace the surfaces, nothing is normally required. But a notification to the municipality is required if you:

  • alter the load-bearing structure
  • move or significantly alter the water and drain stacks
  • change the layout in a way that affects the ventilation

If you live in a housing cooperative apartment (bostadsrätt), you also need the board's written approval before you start demolition. The cooperative's statutes apply, and they differ from one cooperative to the next.

What does it cost?

For a bathroom of 5–7 square metres in the Gothenburg area, fully renovated down to the floor structure, the normal range is SEK 150,000–250,000 including materials and labour.

Item Approximate share
Demolition and waste removal 8%
Building work, floor falls, walls 25%
Waterproofing and tiling 25%
Plumbing 20%
Electrics and ventilation 10%
Sanitaryware, taps, fittings 12%

What drives the price:

  • Replacing or moving the stacks. Moving the floor drain or rerouting the stacks is the single largest cost item and can add 30–50 per cent.
  • Type of floor structure. A timber floor structure requires more build-up and more checks than a concrete one.
  • Tile format. Large-format tiles and mosaic take much longer to lay than standard formats.
  • Older houses. In houses built before the 1970s, there is often something unexpected behind the tiles.

The ROT tax deduction (rotavdrag) covers 30 per cent of the labour cost, up to the annual cap per person. We always split labour and materials in the quote.

A realistic timeline

The most common disappointment in a bathroom renovation is the time it takes. The reason is that the waterproofing and the levelling compound have to dry, and drying time cannot be negotiated away.

Week 1 – demolition and structure

Demolition down to the floor structure, waste removal, checking the substrate. Any moisture damage is discovered here.

Week 2 – plumbing and electrics

Pipework, electrical conduits, underfloor heating, ventilation. All changes that require opening up walls and floors are made here.

Week 3 – build-up and falls

Floor levelling with a fall towards the drain, wall boards, filling. Drying time: several days.

Week 4 – waterproofing

Primer, waterproofing in several coats, sealing collars around penetrations. Each coat must dry according to the manufacturer's instructions. This step cannot be rushed.

Week 5 – wall and floor tiles

Tiling, grouting, silicone.

Week 6 – fitting and handover

Sanitaryware, taps, shower, fittings, pressure testing, self-inspection, quality document and walkthrough.

In total: five to seven weeks for a normal bathroom. If someone promises two weeks, they have either left out the drying times or are planning to cut them short.

Seven questions to ask the contractor

  1. Are you a certified wet-room contractor under BBV or GVK?
  2. Will I receive a quality document and self-inspection record at handover?
  3. Is the plumbing carried out in accordance with Säker Vatten?
  4. What is included in the price – and what costs extra?
  5. How is hidden damage discovered during demolition handled?
  6. What guarantee applies to the work?
  7. Who is my contact person throughout the project?

If you get vague answers to questions 1, 2 or 5 – move on to the next contractor.

Common mistakes

  • Choosing on lowest price. The difference between quotes almost always lies in what is not written in the cheaper one.
  • Skimping on ventilation. An airtight bathroom without working extract ventilation will get damp and mould, no matter how good the waterproofing is.
  • Ordering sanitaryware too late. Delivery times for fittings are often longer than the building work itself.
  • Moving the drain "because it looks nicer". Often the most expensive centimetre in the whole project.